2V/Hz (2x slope): Remove the jumper between TB1-29 and TB1-30
The engineering value of 2V/Hz mode: At the moment of starting the large motor, the generator voltage drops significantly, and the 2V/Hz characteristic makes the voltage drop faster and more, thereby reducing the kW load perceived by the prime mover and accelerating speed recovery. This is particularly crucial for generator sets operating on isolated islands.
2.5 Input power wiring (pay attention to polarity and phase)
SSR 32-12/63-12:90-153 Vac, Terminal TB2-3 is connected to phase C, and TB2-4 is connected to phase B
SSR 125-12:170-305 Vac, Terminal TB2-3 is connected to phase C, and TB2-4 is connected to phase B
Key safety warning: Without using a power isolation transformer, any grounding point in the magnetic field circuit and another grounding point in the generator output may cause damage to the regulator.
Frequency matching:
Direct connection to 50/60 Hz generator output: Install jumper between TB1-25 and TB1-30
Connect special power sources such as PMG (120-240 Hz): Remove the jumper between TB1-25 and TB1-30
2.6 Remote Voltage Regulating Potentiometer
Use the 5 k Ω, 2 W potentiometer provided by the regulator
If only internal voltage regulation is used, install jumper wires between TB1-6 and TB1-7
In high noise environments, the shielding layer should be connected to TB1-30

3. Parallel compensation: detailed explanation of Droop and Cross Current
3.1 Reactive Droop Compensation
Parallel CT installation in phase B (for three-phase sensing) or non sensing phase (for single-phase sensing)
CT should provide 3-5 A secondary current at rated load
Adjust the droop amount through DROOP ADJUST control on the front panel
When running alone, the UNIT/PARALLEL switch should be short circuited to the CT secondary to prevent the injection of droop signals
3.2 Reactive Differential/Cross Current Compensation
Connect the CT secondary of all parallel units in series to form a closed loop (see Figure 2-6 in the manual)
When the currents of each generator are proportional and in phase, the CT signals cancel each other out, and the system voltage does not sag
Key limitation: Cannot be used in parallel with an infinite power grid (Utility)
3.3 CT polarity (key factor determining the success or failure of parallel connection)
CT polarity errors can lead to:
When parallel connected, the reactive power distribution is severely uneven, resulting in circulating current
Excessive current surge during parallel connection may cause tripping
ABC phase sequence: Connect according to Figure 2-3 to 2-5 in the manual
ACB phase sequence: CT secondary leads must be interchanged
4. Debugging and initial operation process
4.1 Pre operation inspection
Confirm that all wiring is correct and secure (refer to manual figures 2-3 to 2-5)
Confirm that the induced voltage tap matches the actual voltage
Confirm that the frequency selection and compensation slope jumper are correct
Confirm that the input power voltage is correct and the fuse is intact
Confirm that the voltage shutdown switch (if any) is in the off position
4.2 No load start-up debugging
Start the prime mover to the rated speed
Close the voltage cutoff switch (if any) and apply excitation
Observe the generator voltage - the following situations may occur:
Possible causes and measures for handling the phenomenon
Overvoltage (+20% or more): If the induction tap is too low or the regulator fails, immediately disconnect the excitation and check the tap
Without voltage, insufficient residual magnetization is established to execute field strength flashing (see section 4.3)
Under voltage (-15% or more), if the induction tap is too high or the speed is insufficient, check the tap and speed
After the voltage is established, the external potentiometer circuit will collapse. Check the TB1-6/7 jumper or potentiometer for an open circuit
Improper adjustment of voltage oscillation (Hunting) STAB (see section 4.4)
Adjust the front panel VOLT control to the rated voltage
Apply load and verify adjustment accuracy ± 0.25%
4.3 Field Flashing
When the residual voltage of the generator is below 6V (SSR 125-12 is below 12V):
The prime mover is stationary
Connect a non grounded DC power supply (not exceeding 12V) to F+(positive pole) and F - (negative pole) through a 25-30 Ω current limiting resistor
Hold for about 3 seconds before disconnecting
Disconnect the input power of the regulator, start the prime mover, and measure the output voltage of the generator
If it is greater than 6V, the voltage should be able to establish itself; Stop the prime mover and reconnect the input power supply
Safety warning: Do not perform flashing operations while the generator is rotating.
4.4 Stability adjustment of STAB
The default position for the STAB factory is clockwise (CW), which ensures stability but has a slow response:
Counter clockwise (CCW) rotation → response acceleration
Excessive CCW → voltage oscillation
Correct method: Rotate CCW until it starts oscillating, then adjust CW until it just crosses the oscillation point
System voltage instability is most likely to occur when there is no load.

5. Troubleshooting: Systematic diagnostic process