Connect the generator power cord: Insert the 25 foot power cord L14-30P plug that comes with the conversion switch into the generator L14-30R socket, and tighten the fixing nut.
Electrical connections and generator settings:
Connect the electrical appliances that require emergency power supply (such as refrigerators and heaters) to the 120V dual socket of the conversion switch to ensure that the total power does not exceed the standard.
Turn on the "RUN" switch of the generator, confirm that the generator battery indicator light is on (indicating that the charging circuit is normal), and complete the first setting.
2. Functional testing process (must be done before first use)
Test purpose: To verify that the automatic switching function of the transfer switch is normal and to avoid failure in emergency situations.
Test preparation: Ensure all connections are complete, connect a small appliance (such as a desk lamp, phone charger), and confirm that the appliance is powered by the power grid normally.
Simulated power-off test:
Unplug the power grid input extension line of the conversion switch and simulate a power outage in the power grid.
Observe the indicator light: The red power grid interruption light will immediately turn on, and the generator will automatically start after 5-10 seconds.
Confirm switch: About 30 seconds after the generator starts, the green generator light will turn on, and the electrical appliances will be powered by the generator normally.
Simulated recovery test:
Re insert the power grid input extension line to simulate power grid recovery.
Observe the indicator lights: both traffic and green lights remain on (5-10 second detection period), then the red light goes out and the electrical appliances resume power supply to the grid.
Confirm shutdown: Wait for 45-50 seconds, the generator will automatically shut down, the green generator light will turn off, and the test is complete.
Exception handling: If a step in the test is not executed as expected, check if the cable connection is secure and if the generator is in the "RUN" position. After troubleshooting, retest.
3. Daily use and emergency activation process
(1) Daily maintenance (non emergency state)
Every month: Check if all cable connections are secure, without damage or aging; Start the generator and run it for 10 minutes to ensure that there are no faults in the generator.
Every 6 months: Conduct a complete test of the transfer switch according to the "functional testing process" to ensure that the automatic switching function is normal; Check the battery level of the generator and recharge it if necessary.
Long term use (exceeding 3 months): Disconnect the transfer switch from the power grid and generator, store the transfer switch in a dry environment, and maintain the generator according to long-term storage requirements.
(2) Emergency use (sudden power outage in the power grid)
No manual operation required: The switch automatically completes the entire process of "detecting power failure → starting the generator → switching power supply".
Key monitoring: Observe the status of the conversion switch indicator light and confirm that it switches as expected; Monitor the fuel level of the generator and replenish fuel if necessary under safe conditions (operate after shutting down the generator and cooling it down).
After the power grid is restored: without intervention, the transfer switch automatically switches back to the grid and shuts down the generator. After the generator cools down, its "RUN" switch can be turned off (or kept on for the next emergency start).
Maintenance and Warranty
1. Key points of maintenance and upkeep
Switch maintenance:
Cleaning: Use a dry cloth to wipe away surface dust. Do not use water or solvents for cleaning to prevent liquids from entering the interface.
Storage: When not in use for a long time, disconnect all connections and place in a dry, ventilated storage box, avoiding direct sunlight and high temperature and humidity environments.
Testing: Conduct a functional test every 6 months to ensure that there are no faults in the internal circuit.
Cable maintenance:
Regularly inspect the cable sheath for any damage or cracking, and ensure that the plug has no signs of oxidation or erosion.
Avoid excessive bending and squeezing during storage to prevent internal core breakage; The generator end cable should be kept away from high-temperature components such as exhaust pipes.
2. Detailed explanation of warranty policy
Warranty period: 1 year from the date of purchase, covering faults caused by material and process defects.
Warranty scope: For quality issues with the main body of the conversion switch and original cables (control cables, power cords), free repair or replacement of faulty components is provided.
Not covered by warranty:
Human damage (such as falling, collision, liquid immersion, overload use).
Unauthorized maintenance and modification (such as splicing cables, replacing non original components).
Normal wear and tear (such as plug contact wear), damage caused by natural disasters or accidents.