Storage conditions: temperature -20 to+50 ℃; Relative humidity (no condensation) maximum 65%; 100% UV resistant; no condensation; There is no additional ozone generation near the storage point.
Maximum storage period (core logic in Table 7): stored in a dry and constant temperature room, with a rust inhibitor inspection method (mineral oil A) of 12 months and a rust inhibitor filling method (B) of 24 months for overseas transportation packaging; Outdoor storage (loss prevention, sun protection, water ingress prevention) has been significantly shortened - overseas packaging A for 6 months/B for 9 months, filling for 24 months, non overseas packaging A does not support inspection methods (only filling for 12 months), B for 6 months/24 months. The hydraulic cylinder for liquid storage must be equipped with a pipeline between the annular chamber and the piston chamber oil port (customer responsibility), and direct sunlight or other heat sources are strictly prohibited - an increase in ambient temperature can cause an increase in hydraulic pressure inside the cylinder.
Storage period inspection: Conduct a comprehensive inspection at least once a year during the storage period, including visual inspection of appearance protection (damage and rust), hydraulic oil (oxidation/acidification control), inspection and lubrication of maintenance free spherical bearings, and protection inspection of mechanical interface mating surfaces; Extend and retract the hydraulic cylinder by at least a few centimeters each year to prevent seal adhesion. Anti seal damage: Rotate 90 ° around the cylinder axis every six rotations when not stored vertically. After checking the packaging, it must be resealed; The sea freight packaging needs to be refilled with new desiccants.
Overdue disposal: When stored for more than six months, the surface of the cylinder body must be coated/treated with anti rust oil, and the mating surface and mechanical interface must be protected; The cylinder storing rust proof oil must be completely emptied before being put into operation; The deformation of the seal cannot be ruled out, and replacement of the seal must be arranged; Storage beyond the period specified in Table 7 requires consultation with Rexroth for protection and operation plans - improper storage can lead to seal embrittlement, rust proof oil resin formation, and potential leakage.

Installation: Cleanliness and Tightening Standards
Four steps for unpacking: remove the packaging → check the integrity according to the delivery note → visually inspect for transportation damage → dispose of the packaging materials according to national regulations.
Cleanliness is a mandatory prerequisite: the hydraulic cylinder and all installation components are dust-free; Cleaning of installation surface; Simultaneous inspection of hydraulic pipelines; Remove dirt, oxide scale, and chips from the pipeline and all connecting surfaces before installation; Use residue free industrial wiping cloth; The inner wall of the welded pipe must be exposed and flushed.
Tightening core rules (derived from DIN EN ISO 4413:2011-04/5.4.2.1): The design of the installation surface of the machine/system must avoid twisting when the hydraulic cylinder is installed; Installation must avoid unexpected lateral loads/radial forces during operation; The stroke length, load, and cylinder installation method must avoid bending and instability at each stroke position. Specific requirements: The load acts along the centerline of the hydraulic cylinder; Protect the piston rod during installation; Spherical bearings, ear shafts, feet, and flange supports must be able to withstand all forces that may occur. Install an adapter strip on the bottom mounting (MS2) to reduce the shear stress of the mounting screws; Protect bolts and bearings during installation of spherical/sliding bearings (cool bolts if necessary); The connectors are designed according to the expected force, and only original bolts are used for the fork shaped bracket; Suggest limiting the swing/tilt angle of the customer side spherical bearing to prevent unexpected forces on the installation components.
Three types of problems that must be minimized for fastening (DIN EN ISO 4413:2011-04/5.4.2.7): excessive deformation of hydraulic cylinders caused by push-pull loads, introduction of lateral or bending loads, and the swinging speed of ear shaft components that require continuous external lubrication.
Pipe joint and pipeline connection: Follow the installation information provided by the joint manufacturer - recommend joints with soft seals at the threaded bolts (pipe thread DIN EN 228-1, metric thread DIN ISO 261); The use of hemp thread and sealant is prohibited as it may cause contamination and malfunction; The connecting pipeline must meet European and international standards; When designing connecting pipelines, assume the maximum load of hydraulic and mechanical systems according to different working conditions (including pressure peaks that need to be determined separately); Select the pipeline size based on the performance data of the hydraulic circuit diagram. Confirm that the oil ports "A (piston chamber)" and "B (annular chamber)" are correctly connected. Maintain a stable and fixed position of the hydraulic cylinder during installation until the fastening is completed; Twist the customer connection components of the swing head to the bottom; It is strictly prohibited to use connecting components to compensate for installation errors; Remove the blocking head protection device only when establishing the corresponding connection.