Domestic production
The first unit of Putian gas power plant in Fujian province goes into operation
On the morning of December 23, 2008, the opening ceremony of the first 3 and 4# storage tanks and gas-fired power plant of the first phase of Fujian LNG Station Line project was held in district, Meizhou Bay, Putian City, Fujian province.
After the completion of the construction of the new 3 and 4# storage tank project, the storage tank capacity of the Fujian LNG station line project will reach 640,000 cubic meters, which can meet the harsh working conditions of 10 generating units that are full and stopped many times a year. The new storage tank will greatly increase the flexibility of gas storage and peak regulation, providing protection for the gas safety of existing users and the flexibility of new users.
According to the plan, between 2015 and 2020, Fujian Province will form a "two vertical and two horizontal, north-south extension" natural gas pipeline network pattern. Among them, the layout of the ring network is from Zhangzhou along the Zhanglong Expressway to Longyan, from Fuzhou along the Jingfu Expressway to Nanping, and then from Nanping to Zhangping, Yongan, Sanming, Shaxian to Longyan, and the current Fuzhou-Zhangzhou pipeline to form a "two vertical and two horizontal" ring gas supply network structure, which is used as a gas supply platform to connect the corresponding gas transmission branch lines and set up sub-transmission stations, covering the main gas market in the province. The "north-south extension" dispatching line refers to from Fuzhou to Ningde, Fuan, north to Fuding; From Xiamen Xiang 'an through Zhangzhou and Zhangpu south to Zhao 'an, people in Fujian Province can use clean and environmentally friendly natural gas at the same time.
At the same time, the Putian Gas Power Plant #1 unit, which uses the heavy-duty 9F gas-steam combined cycle generator set, successfully passed the 168-hour trial operation before and is now officially put into operation. It is reported that the first phase of the Putian gas power plant project will build four sets of generators, the total investment of the project is 5.08 billion yuan, and the annual power generation will be 6 billion KWH after the first phase of the project is put into operation. The use of clean energy LNG in the power plant can effectively promote energy conservation and emission reduction, improve the conversion rate of primary energy to secondary energy, and reduce carbon dioxide emissions by about 2 million tons per year. The #2 unit under construction has completed part of the engineering commissioning and is expected to be put into trial operation in April 2009 .
China's largest liquefied natural gas reserve base has been put into operation
On September 26, 2022, CNOOC announced that the "Green Energy Port" of CNOOC Yancheng successfully received and unloaded the first ship of LNG, marking the realization of the largest liquefied natural gas reserve base in China