3. Complete acceptance of water intake project and obtain water intake license
Where a mine project water intake project or facility is completed and has been in trial operation for 30 days, the construction unit shall submit relevant materials to the water intake examination and approval authority and apply for a water intake license. The examination and approval authority for water intake shall, within 20 days after receiving the materials, conduct on-site verification of the water intake project or facility and issue opinions on acceptance. For those that pass the acceptance inspection, a water drawing license shall be issued.
4. Complete the acceptance of safety facilities
The construction unit completes all the construction contents in accordance with the approved safety facility design, and if it meets the conditions for completion acceptance, it shall organize the completion acceptance of the safety facilities of the construction project. If the construction unit implements multi-level management, its superior unit with independent legal personality (or company headquarters) can also be responsible for organizing inspection and acceptance. The safety supervision department shall supervise and verify the completion and acceptance activities and acceptance results of mine projects.
5. Complete the acceptance of occupational disease prevention facilities
Before the inspection and acceptance of the occupational-disease-prevention facilities, the construction unit shall work out the inspection and acceptance plan and submit a written report to the work safety supervision and administration department. The principal person in charge of the construction unit or its designated person in charge shall organize occupational health professionals to review the evaluation report on the control effect of occupational disease hazards, check and accept the occupational-disease-prevention facilities, and form review opinions and acceptance opinions. The construction unit shall make a written report on the acceptance process of the occupational-disease-prevention facilities for future reference. The construction project with serious occupational-disease-prevention hazards shall submit a written report to the work safety supervision and administration department.
6. The coal mine project shall carry out joint trial operation
After the completion of a coal mine project, joint trial operation shall be carried out before the completion and acceptance. The project construction unit shall prepare a joint trial operation plan and report it to the provincial coal industry administrative department for the record. After the completion of the joint test run, the construction unit shall prepare a joint test run report.
7. Coal mine projects shall implement capacity replacement requirements
The State Council and the National Development and Reform Commission have stipulated that since 2016, the new coal production capacity reduction and replacement policy has been implemented, and the new coal mine projects have to implement the reduction and replacement, and the coal mine projects need to provide the capacity replacement plan before the application for approval, and the project approval authority will review and approve the capacity replacement plan according to the requirements. In order to promote the acceleration of the construction of advanced capacity coal mines, the state will review and confirm the capacity replacement plan of coal mine projects in 2022, and adjust it from the project approval to the completion acceptance.
8. Complete the project completion acceptance
Where a mine project has been completed in accordance with the approved construction scale, standards, investment and contents, meets the design and production requirements, and environmental protection facilities, soil and water conservation facilities, safety facilities, etc. have been completed in accordance with the requirements and passed the special acceptance inspection, meeting the acceptance conditions, the construction unit shall organize the completion acceptance inspection. After the mine project has passed the acceptance check, the construction unit shall submit the opinions on the completion acceptance check, the rectification report of the enterprise on the completion of the completion acceptance check, the notice of the completion acceptance check (the appraisal letter) and other materials to the competent administrative authority.
9. Obtain safety production license
China implements a safety production licensing system for mining enterprises. Before a mine project is put into operation, it shall apply to the relevant administrative authority for issuing a safety production license. Mining enterprises that have not obtained safety production licenses shall not engage in production activities. It should be noted that coal mine projects and non-coal mine projects should handle safety production permits in accordance with the Measures for the Implementation of Safety Production Licenses for Coal mine Enterprises and the Measures for the Implementation of Safety Production Licenses for non-coal mine Enterprises, respectively.